Lübeck (DE)

Logistics hall at the Skandinavienkai

WIEHAG was commissioned with the structural analysis, planning and delivery of the timber elements for construction of a new logistics hall in Lübeck.
The timber components with a length of up to 48 metres were delivered in 65 special transports. A large-scale project with logistical challenges that WIEHAG successfully mastered.
Project background

A large-scale project at the port of Lübeck

Skandinavienkai in Lübeck is the largest ferry port on the Baltic. In 2019, the Lübeck Port Authority (LPA) commissioned construction of a 300 m long, 120 m wide and 15 m high logistics hall. The bearing system and the roof and wall panels had to be made of timber. This required a total of:

  • 31 double tapered beams with a length of approx. 28 m
  • 31 fish-bellied girders with a length of approx. 43 m
  • 31 fish-bellied girders with a length of approx. 48 m
  • 16 parallel beams with a length of approx. 48 m
  • Approx. 18,000 metres of bracing and tension bars
[Translate to Englisch:] Logistikhalle am Skandinavienkai

Special transport of a 48 m girders to Lübeck

Skip slider
wiehag-transport-skandinavienkai
Jump to slider start
Delivery

Logistics from WIEHAG

WIEHAG supplied the components for the roof supporting structure and the wall construction. Numerous special transports and extra-long transports were required for this purpose:

  • 32 special transports and 28 standard transports or extra-long transports up to 24 metres for the roof structure
  • 5 extra-long transports up to 22 metres for the wall construction

The total delivery time was seven weeks. The components were assembled by Mohrmann Bau GmbH.

[Translate to Englisch:] Logistikhalle am Skandinavienkai Innenansicht
  • Logistics hall on the Skandinavienkai
    A large-scale project
    The logistics hall on the Skandinavienkai was above all a logistical challenge: Bringing the support structure for a 36,000 m² hall to northern Germany was only possible with good planning.
    — Markus Gasselsberger, WIEHAG project manager
Other references

Discover WIEHAG’s engineering skills

Skip slider
  • Culture, Sports and leisure centres
Wels Exhibition Centre
  • Logistics, retail, industry
AMAG Austria Metall AG
  • Culture, Sports and leisure centres
New Karlsruhe Exhibition Centre
  • Logistics, retail, industry
Thalmeier Joinery
  • Logistics, retail, industry
Haidl Atrium
Jump to slider start
YouTube is deactivated

We need your consent to use YouTube videos. For more information, see our Privacy Policy.

Vimeo is deactivated

We need your consent to use Vimeo videos. For more information, see our Privacy Policy.

Google Maps is deactivated

We need your consent to use Google Maps. For more information, see our Privacy Policy.